The objective of this activity was to construct the dredging equipment, but also to build the treatment system to take care of the dewatering and the rejected water.
The aim of this activity was to construct and assemble the dredging units that are used on the test site in the bay of Malmfjärden.
Because of problems with the original prototypes, the construction phase of the dredging units took longer than expected. In spring 2020, a new dredging unit, Mudster, was finally ready.
The dredging system Mudster consists of three main components:
The treatment site is a small area close to the test location, where the dredged masses are collected, dewatered and the reject water is treated and then released. In order to steer and control the uptake and treatment of the sediment, a special program was developed for LIFE SURE.Read more about the unique design solutions of the dredging units and dewatering system in the design document
LIFE SURE has produced several films, presenting the concepts and solutions developed in LIFE SURE.
Agreement with suppliersThe planning and preparation included all processes of public tendering and purchase of equ
To know how to fully use the equipement in full scale, we will first test the system in small scale.
Based on the knowledge of the small scale test, we will perform full scale dredging and treatment.
The focus for monitoring and evaluation is mainly to follow up the effects of the dredging activities.
How to disseminate the technology and results of Life SURE.
LIFE SURE will ensure that the solutions developed in the project can be used throughout the EU